Making Changes to Your Land

Subdivision is the process of legally dividing a parcel of land into two or more lots or adjusting existing title boundaries. Subdivision approval is also required for title separations, bareland condominiums, and the registration of long-term leases. Whether you are creating a new residential lot, subdividing farmland, or reconfiguring property lines, the subdivision process helps ensure that new lots are appropriately serviced, accessible, and consistent with municipal planning bylaws and policies as well as provincial legislation.

The Oldman River Regional Services Commission (ORRSC) administers the subdivision process on behalf of our member municipalities. Our subdivision services include reviewing, screening and processing applications, formulating recommendations, registering deferred reserve caveats, and endorsing subdivision finalizations.

This page provides an overview of the subdivision process, application requirements, and resources to help guide you through each stage of the process.

Subdivision Application Package

Choose the package for your property

Rural subdivision application package cover

Rural

Subdivision application package

Download PDF
Urban subdivision application package cover

Urban

Subdivision application package

Download PDF

Additional forms

For both rural and urban applications

Extension Request Form

Download PDF

Withdrawal Request Form

Download PDF

BEFORE YOU APPLY

How do I start?

Before you submit an application, we highly recommend that you or your representative contact a Planner to discuss your proposal prior to submitting an application to:

Discuss your site

Discuss site suitability and conformity with local and provincial planning regulations.

Understand what's required

Assist you in determining whether additional processes and professional services will be required and what additional costs you may incur.

Open houses

Have a project in mind?

Visit your municipality’s page to find the Planner for your area and their contact information. Reach out by phone or email to discuss your proposal or set up an in-person meeting.

Application Requirements

You will need to submit the following with your subdivision application:

A completed application form signed by either the registered owner(s) of the land or the person authorized to act on their behalf.

Application forms are available at the top of this page or at your municipal office.

Fees are payable to the ORRSC and are non-refundable. Fees may be paid by debit, cash, cheque or e-Transfer to subdivision@orrsc.com. More detailed fee information is available in the Fees section below.

A current copy of the Certificate(s) of Title for the land you are proposing to subdivide. The title(s) must be dated no more than 30 days prior to the application submission. If you are proposing to consolidate land, please include title(s) to all of the lands involved.

A current copy of the Certificate(s) of Title may be obtained from any provincial registry office or online at www.spin.gov.ab.ca OR https://landregistry.alberta.ca/.

An accurate and legible sketch (drawn to scale) that shows the location, dimensions and boundaries of the proposed parcel in relation to the land being subdivided and all the requirements identified in the Subdivision Sketch Checklist included with the application form. The sketch must include dimensions from all buildings and structures (including private septic systems) to existing and proposed property lines. Sketches without dimensions will not be accepted.

If the land being subdivided has any buildings or structures and is located within an urban municipality (village, town, or city), hamlet, or Vulcan County, M.D. of Willow Creek No. 26 and the Municipality of Crowsnest Pass, your sketch must be prepared by an Alberta Land Surveyor.

In accordance with the Matters Related to Subdivision and Development Regulation: A map from the AER identifying the presence or absence of abandoned wells on the land being subdivided;*

AND

EITHER a statement that there are no abandoned wells on the land being subdivided OR a list and map identifying the location of abandoned wells (including the surface coordinates) on the land being subdivided.*

*This information can be obtained from the AER’s Abandoned Well Viewer (https://maps.aer.ca/awm/index.html) or by contacting the AER Customer Contact Centre by telephone (1-855-297-8311) or by email (inquiries@aer.ca).

If an abandoned well is found to be present on the land being subdivided (subject parcel), a tentative plan of subdivision (for vacant parcels) or survey sketch (for parcels that contain buildings and improvements) prepared by an Alberta Land Surveyor that illustrates the actual well location on the subject parcel as identified in the field and the setback established in the AER Directive 079 in relation to existing or proposed building sites may be required.

You may be required to submit additional information such as a water report in accordance with the Water Act, professional soils tests and analysis demonstrating suitability of private sewage treatment systems, geotechnical reports, and other professionally prepared reports, concept plans, and any other information necessary to determine whether the application meets the requirements of Section 654 of the Municipal Government Act.

Fees

Costs of a subdivision can vary greatly from application to application and are based on the number and type of lots created. Some of the basic costs that you can expect are outlined below.

Application and Finalization fees are payable to the Oldman River Regional Services Commission (ORRSC) and are non-refundable. Fees may be paid by debit, cash, cheque or e-Transfer to subdivision@orrsc.com.

Subdivision Application & Finalization

Application Fee This fee is due when you submit your application. The application fee is based on the number of lots to be created. There is a base application fee of $800 plus an additional $400 per lot created.

Endorsement Fee This fee is payable at the time of endorsement. The fee for endorsement is $250 per lot.
Application Fee
$800
Per Lot Fee
$400
Endorsement Fee
$250
$800 Plus $400/Per Lot $250/Per Lot
Payable with Initial Application Payable Prior to Endorsement

Example: Subdividing a farmstead from a quarter section or creating two lots from an existing title:

Application Base Fee $800
Per Lot Fee $400
Subtotal $1,200
Due at time of application
Endorsement Fee (per lot) $250
Subtotal $250
Due prior to endorsement
Total $1,450

OTHER ORRSC FEES

Extension Fee
If you are unable to finalize your subdivision within one year from the date of decision, you must request an extension. A $375 fee is applicable at the time of your first request. Fees increase in $100.00 increments for each subsequent request.

Recirculation Fee
Prior to a decision being made, minor changes to an application may be accepted at the office with no additional costs; however, if the change requires the application to be recirculated to the various agencies and adjacent landowners, there will be a fee of $400.

ALL ORRSC SUBDIVISION FEES ARE NON-REFUNDABLE.

AGENCY/PROFESSIONAL FEES

You may incur additional costs from review agencies and/or professionals for services such as:

Surveying
Surveying is often required to show the location of structures, prepare plans and to register documents with the Land Titles Office. The Land Titles Act requires an Alberta Land Surveyor (ALS) to be used for this purpose. Surveyors should be contacted for estimates of the job. Click here for a list of Alberta Land Surveyors available in southern Alberta.

Municipal Reserve Payment
Municipal Reserve will normally be taken in accordance with the Act except as follows:

  • one lot is to be created from a quarter section
  • land is to be subdivided into lots of 40 acres or more and is to be used for agriculture
  • land to be subdivided is 2 acres or less
  • reserve was previously satisfied

The 10% municipal reserve requirement may be taken as land or cash in lieu of land based on the pre-subdivision market value of the land. Market value may be assessed by the municipality or you may provide a professional appraisal.

Land Titles Fees
The Land Titles Office charges registration fees for subdivision and related documents.

Irrigation District Fees
If the land being subdivided is within an irrigation district, there may be additional fees required to amend the delivery system or provide domestic water agreements.

Installation of Municipal Services
The cost of providing municipal services are usually the responsibility of the developer. This would include the costs for utilities provided by various utility companies. Some municipalities require off-site levies at the time of subdivision or development.

Costs of Other Professional Services
Other information may be required to process your application or meet the conditions of approval which may include, but are not limited to:

  • Legal fees
  • Geotechnical analysis
  • Slope stability analysis
  • Private sewage disposal system assessment
  • Civil engineering analysis
  • Biophysical assessment
  • Wetland analysis
  • Historic archaeological surveys
  • Ground and surface water analysis
  • Underground fuel tank inspections
  • Area Structure Plan preparation

PLAN YOUR SUBDIVISION

Your Subdivision, Step by Step

From application submission to subdivision registration

 

Subdivision Process

Understanding the subdivision process can help you know what to expect and prepare for each stage of the application. While every application is unique and timelines may vary depending on its complexity, the following steps provide an overview of the typical subdivision review and approval process from application submission to registration.

Subdivision applications are processed and approved in accordance with the Municipal Government Act. A majority of the approval processes discussed below are legislated and the time periods for completion of the steps are established in the Act. As the subdivision process is legislated by the province, there is often little ability to vary the timelines. Once your subdivision application arrives in our office, the subdivision will follow the following steps:

We will review your application for completeness. We must determine whether your application is complete within 20 days of receiving it.

If additional information is required, your application may be deemed incomplete. You will receive a written request for information and be given additional time to submit the required items.

Notice of the subdivision application will be circulated to the municipality, any adjacent municipality, the applicant, the landowner, adjacent landowners, school boards, utility companies and any government departments required to be notified under the Matters Related to Subdivision and Development Regulation.

Our circulation notices have a minimum response time of 19 days.

Following the end of the circulation process, a recommendation to the municipality’s Subdivision Authority is prepared by the Planner.

The Planner’s recommendation will take into consideration the following:

  • Legislative requirements
  • The Land Use Bylaw, and adopted statutory plans including Intermunicipal Development Plans, Municipal Development Plans, and Area Structure Plans.
  • Responses received during the circulation process
  • Relevant planning issues
  • Evidence from site inspections

The Subdivision Authority considers responses to the circulation, the recommendation and, where received, adjacent landowners’ comments. The Subdivision Authority for the appropriate municipality will make a decision which may be an approval, an approval with conditions, or refusal. A decision is required within 60 days of the application being deemed complete, unless you agree to extend that time period. The decision is sent to you and those notified prior to the decision being made, except adjacent landowners.

In approving a subdivision, a Subdivision Authority may place a number of conditions on a subdivision approval. Some of the more common conditions and steps to satisfy them include:

  • Taxes: payment of any outstanding property taxes per MGA s.654(1)(d).

    Submit a paid tax receipt or a letter from the Municipality indicating that taxes are paid for the current tax year.

  • Development Agreement: a Development Agreement ensures that any infrastructure the Municipality requires (services, roads, approaches, etc.) are constructed in accordance with municipal standards.

    Contact the Municipality to determine whether you need to enter into a Development Agreement with them. ORRSC requires either a copy of the signed Development Agreement or a letter from the Municipality indicating that no development agreement is required.

  • Municipal Reserve: paying or providing municipal reserve which is either land or money in lieu of land or a combination of both for park or school purposes.

    This payment is made to the Municipality. ORRSC will require a letter verifying that the payment was made. We will prepare any deferred reserve caveats or discharges if they are required.

  • Environmental Reserve: dedicating land that contains or is adjacent to certain environmental features in the form of a titled parcel in the name of the municipality or an easement requiring the land remain in its natural state.

  • Survey Plan: a final plan of survey for the subdivision is required to confirm the final location of property boundaries.

    Contact your surveyor so they can begin preparing your survey plan, including fieldwork, monument placement, and documents. To register the subdivision plan, the surveyor will need Consent Forms from all titled landowners.

    Discuss with your surveyor and/or agent what they will assist with and which responsibilities will remain with you. For example, if right-of-way or easement drawings or agreements are required, clarify who will initiate them.

  • Easement or right-of-way: provision of any easements or rights-of-way that may have been required by utility companies or the municipality for access or services.

    The “Informative” section of the subdivision approval will include responses from affected utility companies and provide direction on how to initiate the process. You will need to sign a legal agreement with the parties and may also require a plan of survey to delineate where the easement or right-of-way is located.

You are responsible for ensuring all conditions are satisfied and providing written confirmation to ORRSC. Conditions must be met within one year of the date of approval. If you are unable to complete the conditions within one year, you may apply for an extension while you are within that one-year timeframe.

When all the conditions are met and the appeal period has lapsed, ORRSC is able to endorse the plan or other instruments at your request. To initiate the finalization process, your surveyor or lawyer will provide the final documents to ORRSC:

  • for a review to ensure final plans reflect the decision made by the subdivision authority.
  • to ensure all conditions are met.
  • for the necessary consent and authorization documents required by the Land Titles Office.

 

After signing, the instrument is returned to the surveyor, lawyer or other person directed by the applicant to proceed with registration. The subdivision file is then held at the ORRSC office for an indefinite period.

Once your subdivision is endorsed, you, your surveyor or lawyer must submit the endorsed subdivision package to the Land Titles Office for registration along with any other required documents or agreements that must be registered at the same time. Upon registration, new certificates of title will be issued by Alberta Land Titles for each parcel created and the subdivision is complete.

Appealing a Decision

The Subdivision Authority’s decision, including any conditions of approval, can be appealed. Depending on the location and nature of the land, your appeal will be heard by either the Land & Property Rights Tribunal or your municipality’s Subdivision & Development Appeal Board.

Calendar 21

Deadline to Appeal

Appeals may be made within 21 days of the date of the decision letter.

Who can appeal?

The Applicant (you) Government departments School boards on the matter of municipal reserve Adjacent landowners cannot file an appeal.

Submitting an Appeal

An appeal must be made in writing and contain reasons for the appeal. Where you file the appeal depends on who has the jurisdiction to hear your appeal. See below.

Where does your appeal go?

Swipe across to compare both appeal boards →

PROVINCIAL LPRT Land & Property Rights Tribunal MUNICIPAL SDAB Subdivision & Development Appeal Board
Applies when

In accordance with the Municipal Government Act, an appeal lies with the Land & Property Rights Tribunal (LPRT) when:

  • the land being subdivided contains, is adjacent to or is within the prescribed distance of a highway, a body of water, a sewage treatment or waste management facility or a historical site.
  • the land is subject to a licence, permit, approval or other authorization granted by the Natural Resources Conservation Board, the Energy Resources Conservation Board, Alberta Energy Regulator, Alberta Energy and Utilities Board or the Alberta Utilities Commission.
  • the land is subject to a licence, permit, approval or other authorization granted by the Minister of Environment and Protected Areas or the Minister of Forestry, Parks and Tourism.

When the appeal does not lie with the Land & Property Rights Tribunal (LPRT), the municipal Subdivision and Development Appeal Board (SDAB) holds jurisdiction over the appeal.

Filing fee
There are no fees for appeals filed to the LPRT. Many municipalities require a fee to file an appeal. Contact your municipality for further information on filing an appeal with the municipal SDAB.
At the hearing
Parties can provide input and may be questioned.
After the hearing
Further appeal is available on a point of law or jurisdiction.
Hearing timeline
60 days Hearing held within 60 days. 30 days Hearing held within 30 days.
Decision
15 days from the conclusion of the hearing.
More information
More about LPRT appeals → More about SDAB appeals →

Frequently
Asked Questions

Generally, a subdivision application is needed when a person wishes to have an existing land title divided into one or more additional titles or to re-orient the boundaries of a title.  For example, if your land title contains 10 acres and you want two titles of 5 acres each, a subdivision application is required.

Other instruments requiring subdivision approval include the creation of bareland condominiums and the registration of long-term leases.

Two exceptions to this are allowed under the Act:

  • the separation of a parcel described as a quarter section
  • where two or more lots from a registered plan are contained within a title, those lots may be separated if the plan was registered after July 1, 1950

 

In each of these cases, you may apply directly to the Land Titles Office.

Planners are available to discuss subdivision proposals and applications. Planners often work both in the office and in the field, so please email or leave a phone message regarding the matter or to schedule an appointment. Contact information for your municipality’s Planner can be found here. Generally, development matters should be initiated with the municipality first.

The registered owner of the land or a person authorized to act on their behalf may make an application for subdivision.

Timelines vary depending on the complexity of the application, circulation requirements, and completion of approval conditions. Once a subdivision application has been deemed complete, the Subdivision Authority has 60 days to make a decision.

If your subdivision is approved, you have one year to meet all their conditions and submit final documents and plans for endorsement by ORRSC. A subdivision cannot be endorsed, even if all conditions have been met, until the 21-day appeal period has lapsed. After endorsement, the subdivision must be registered with the Land Titles Office within one year.

Yes, approval is valid for one year. If you are not able to fulfill the conditions and apply for endorsement within one year of approval you must apply for an extension to extend the validity of the approval. After endorsement, the subdivision must be registered with the Land Titles Office within one year.

The rules for subdivision are set by the provincial government through the Municipal Government Act and the Matters Related to Subdivision and Development Regulation. Each municipality establishes their own subdivision policies through their Land Use Bylaw, and adopted statutory plans including Intermunicipal Development Plans, Municipal Development Plans, and Area Structure Plans.

The following information is required when submitting an application for subdivision, otherwise the application shall be deemed incomplete.

  • Application Form
  • Application Fee
  • Current Copy of Title obtained within the last 30 days
  • Sketch of the Proposed Subdivision
  • Alberta Energy Regulator (AER) Abandoned Well Information
  • Any other information requested by the Planner

You may be required to submit additional information to determine whether the application meets the requirements of Section 654 of the Municipal Government Act. Additional information may include, but is not limited to:

  • Geotechnical analysis
  • Slope stability analysis
  • Private sewage septic soils evaluation
  • Civil engineering analysis
  • Biophysical assessment
  • Wetland analysis
  • Historic archaeological surveys
  • Ground and surface water analysis
  • Underground fuel tank inspections

Prior to a decision being made, minor changes to your application may be accepted at the office with no additional costs; however, if the change requires your application to be recirculated to the various agencies, there will be a fee of $400.

It is recommended that you speak with your Municipality’s Planner before proposing any changes.

Generally, you need a subdivision application when you want to have an existing land title divided into one or more additional titles. 

Two exceptions to this are allowed under the Act:

  • parcels that are divided by a quarter section line
  • where two or more lots from a registered plan are on a title, those lots may be split if the plan was registered after July 1, 1950

 

In each of these cases, you may apply directly to the Land Titles Office.

Subdivision plans must be prepared by an Alberta Land Surveyor. Click here for a list of surveyors available in southern Alberta.

No, once final endorsement is received your subdivision needs to be registered with the Alberta Land Titles Office who will issue new land titles upon registration.

Where a proposed property line goes through an existing building, the building may need to be removed, relocated or demolished prior to receiving the final subdivision endorsement if it was required as a condition of the subdivision approval. A demolition permit may be required through the municipality.

If there is an existing semi-detached dwelling, rowhouse, or multi-unit dwelling on the site and it will remain, the common party wall(s) must coincide with the proposed subdivision line(s) and must be identified on the Plan of Subdivision. A party wall agreement may be conditioned by the subdivision approval. Additionally, the common party wall must meet requirements of the Alberta Safety Codes. A building permit may be required to bring the party wall up to appropriate standards.

If an existing building is to remain on the site it is subject to the setback requirements of the Land Use Bylaw.

Yes, within 21 days of the date on the letter giving notice of the decision, an appeal may be filed. Appeals can only be made by:

  • government departments
  • school boards on a matter of municipal reserve
  • the applicant (you)

Adjacent landowners cannot file an appeal. 

See Appealing a Decision.

Municipal reserve (MR) is land, or money in place of land, that you may be required to give to your municipality when you subdivide. Under Alberta’s Municipal Government Act, the municipality can take up to 10% of the land being subdivided, after any environmental reserve is subtracted. This land is used for public purposes such as parks, playgrounds, sports fields, trails, and school sites. In some cases it may be called municipal and school reserve or school reserve.

The municipality may take money instead of land (cash-in-lieu), usually when a land dedication wouldn’t be practical, such as on a small subdivision. That money goes into a reserve fund for parks, recreation, and school purposes. The municipality can also defer reserves to a future subdivision. This is done by registering a deferred reserve caveat on the title.

Environmental reserve (ER) is land that isn’t suitable for development because of its natural features. The municipality can require it to be dedicated when land is subdivided. ER can include:

  • Swamps, gullies, ravines, coulees, and natural drainage courses
  • Land that is flood-prone or unstable
  • A strip of land at least 6 meters wide along the bed and shore of a lake, river, stream, or other body of water

Environmental reserve protects these areas from development, prevents pollution, and can provide public access to waterways. ER is generally left in its natural state or used as a public park. ER does not count toward the 10% municipal reserve. Instead of taking ownership of the land, you and the municipality may agree to an environmental reserve easement. With an easement, the land stays privately owned but is still protected.

Reserve requirements are determined by the Subdivision Authority for each application.